3. Restoration of a facility to its original condition following damage from fire, accident, disturbance, or natural calamity.
DOC 335.05(3)(b)1.1. Grant of easements across department property for the purpose of below-ground construction of utilities, including pipelines and transmission lines.
DOC 335.05(3)(b)2.
2. Maintenance of buildings, including but not limited to replacement of doors, windows and roofs, and painting, without altering the architectural integrity of the buildings.
DOC 335.05(3)(b)3.
3. Maintenance of roads, sidewalks, curbs, and gutters at institutions.
DOC 335.05(3)(b)4.
4. Road and parking lot resurfacing on department properties, and expansion without significant extension or relocation.
DOC 335.05(3)(c)
(c) Legislative proposals. Positions of the department on legislative proposals originating outside the department.
DOC 335.05(3)(d)
(d) Research. For purposes of this paragraph,“research" means systematic investigation designed to develop or contribute to generalizable knowledge.
DOC 335.05(4)
(4) Other actions. Every action not fitting into one of the categories in
subs. (1) to
(3) shall be evaluated for determination of type.
DOC 335.05(5)
(5) Updating of type-list. The action type-list shall be updated from time to time by rulemaking to reflect change in department programs or change in the categorization of department actions.
DOC 335.05 History
History: Cr.
Register, March, 1992, No. 435, eff. 4-1-92.
DOC 335.06
DOC 335.06 Determination of need for an EIS. DOC 335.06(1)(1) During the early planning of an action, the department shall determine the need or desirability of preparing an EIS on the proposed action, in accordance with
ss. DOC 335.05 and
335.07.
DOC 335.06(2)
(2) The department shall prepare an EIS for all type I actions, and for all type II actions which are found to significantly affect the environment of human beings.
DOC 335.06(3)
(3) The department may prepare an EIS on any other action at any time to assist planning and decisionmaking for the action.
DOC 335.06(4)
(4) If the department decides to prepare an EIS, it does not need to prepare an EA.
DOC 335.06 History
History: Cr.
Register, March, 1992, No. 435, eff. 4-1-92.
DOC 335.07
DOC 335.07 Preparation of environmental assessment. DOC 335.07(1)(1) Except as provided in
s. DOC 335.06 (4), to determine whether a type II action is major and significantly affects the quality of the natural and physical environment of human beings, and to describe alternatives to that action, the department shall conduct an environmental assessment and shall prepare a reviewable record in the form of a concise report. This shall be done as early as possible in the planning process but, in any event, before contracts are signed if the action involves construction. The report shall include:
DOC 335.07(1)(a)
(a) A description of the proposed action, to include the purpose of the action and need for the action;
DOC 335.07(1)(b)
(b) A description of those elements of the environment of human beings which are affected by the proposed action;
DOC 335.07(1)(c)
(c) Identification and discussion of the most significant effects on the environment that can be reasonably foreseen if the proposed action is carried out. “Effects" are of 2 types:
DOC 335.07(1)(c)1.
1. Primary effects are those on the resources of water, air, land, plants, animals, energy use, historic properties, wilderness, vistas, and tranquillity which is affected by noise. Primary effects also include those on society and economy, but only when the effects on society and economy are inter-related with the foregoing resources.
DOC 335.07(1)(c)2.
2. Secondary effects are, in relation to primary effects, the foreclosure of future options, establishment of precedents, cumulative impacts when actions of the type are repeated, stimulation of indirect effects, conflicts with official plans of public agencies or with policies of governments at any level, and significant controversy that may be or is generated by the proposed action.
DOC 335.07(1)(d)
(d) A consideration of reasonable alternatives to the proposed action, including the alternative of no action, and the identification of the significant environmental effects of these alternatives when they differ from the anticipated impacts of the proposed action; and
DOC 335.07(1)(e)
(e) A list of agencies and persons consulted, with synopses of the comments and other pertinent information provided by these agencies and persons.
DOC 335.07(2)
(2) Where proposed actions are likely to be repeated on a recurring basis or where they have relevant similarities such as common timing, impacts, alternatives, methods of implementation, or subject matter, a generic EA may be prepared. The department shall, when addressing a single action already covered by a generic EA, consider the relevance of the generic EA to the specific action.
DOC 335.07(3)(a)(a) The department shall develop a notice that the EA has been prepared and is available for review, which shall include the following information:
DOC 335.07(3)(a)2.
2. A brief description of the proposed action, to include the location of any project;
DOC 335.07(3)(a)3.
3. The preliminary determination by the department of the need for an EIS;
DOC 335.07(3)(a)4.
4. The name of a contact person within the department who can supply copies of the EA and can answer questions about it; and
DOC 335.07(3)(a)5.
5. The latest date on which the department will accept and consider comments before making a final decision on the need for an EIS.
DOC 335.07(3)(b)
(b) The department shall send copies of the notice to all individuals, agencies, and organizations that have requested notification of the EA or of all EAs and, in the case of a project in a particular area of the state, to appropriate news media in the vicinity of the project. The department may also publish the notice in the Wisconsin Administrative Register.
DOC 335.07(3)(c)
(c) Following the deadline for receipt of public comment on the EA, the department shall review the EA, consider the comments received on it, make modifications judged necessary, and approve the EA which shall include a finding either of no significant impact or of the need for an EIS.
DOC 335.07(4)
(4) If a finding is made in the EA of no significant impact, no EIS shall be required, the environmental review is complete and the original EA shall then be filed in the department's offices in Madison, Wisconsin and at the county clerk, city clerk or town clerk in the area of the project. Such a finding shall be the final decision of the department which may be appealable as a contested case under
ch. 227, Stats.
DOC 335.07(5)
(5) If a finding is made in the EA that an EIS is required for the proposed action, the department shall proceed with preparation of an EIS.
DOC 335.07 History
History: Cr.
Register, March, 1992, No. 435, eff. 4-1-92.
DOC 335.08
DOC 335.08 Preparation of environmental impact statement. DOC 335.08(1)(a)(a) As soon as possible after the decision to prepare an EIS, the department shall inform the public and affected or otherwise interested agencies that an EIS will be prepared and that the process of identifying impacts and alternatives to be analyzed in the EIS is beginning.
DOC 335.08(1)(b)
(b) The scoping process shall include, to the extent possible, affected federal, state and local agencies, any affected Indian tribe, and other interested persons. The process may consist of meetings, hearings, workshops, surveys, questionnaires, interagency committees, or other appropriate methods or activities, and may be integrated with other public participation requirements.
DOC 335.08(1)(c)1.
1. Determine the parameters of the EIS and the significant issues to be analyzed in depth in the EIS; and
DOC 335.08(1)(c)2.
2. Identify and eliminate from detailed study the issues which are not significant or which have been covered by prior environmental impact analyses. This will permit limiting the discussion of these issues in the EIS to a brief presentation about why they are not significant for the human environment or to references to other documents in which these issues are discussed.
DOC 335.08(2)(a)(a) The EIS shall be written in plain language, and shall be concise, clear, and to the point. It shall include appropriate graphics to help decisionmakers and citizens understand the implications of the proposed action and alternatives for quality of the human environment.
DOC 335.08(2)(b)1.
1. A cover sheet containing the title of the proposed action, name of the department, designation of the document as the draft or final statement, name and address of the office where more information can be provided, a one-paragraph abstract of the statement and the last date on which comments on the document will be considered.
DOC 335.08(2)(b)2.
2. A summary of the statement. It shall briefly describe the proposed action and shall emphasize major conclusions, areas of controversy, and issues to be resolved.
DOC 335.08(2)(b)5.
5. A succinct description of the environment which would be affected by the proposed action.
DOC 335.08(2)(b)6.
6. In comparative format, an analysis of the impact on the environment of the proposed action and all reasonable alternatives to it, including the alternative of no action.
DOC 335.08(2)(b)7.
7. A discussion of the scientific and analytic bases for the environmental consequences identified in
subd. 6.
DOC 335.08(2)(b)9.
9. Appendices, if any, relevant to analyses in the EIS or otherwise relevant to the decision to be made.
DOC 335.08(2)(c)
(c) Other documents and sources of information may be incorporated by reference if they are available for public inspection at the central offices of the department in Madison and at the county clerk, city clerk or town clerk in the area of the project.
DOC 335.08(3)(a)(a) When an EIS is required, first a draft EIS and then a final EIS shall be prepared by the department or else be prepared for the department under contract by a consultant with supervision and final editorial review by the department. The EIS shall emphasize significant environmental issues identified during the scoping process. An EIS shall contain, in the appropriate parts specified in
sub. (2) (b) 4. to
7.:
DOC 335.08(3)(a)1.
1. A description of the proposed action and of the affected environment, including the project location, type of facility, time schedules, maps and diagrams deemed relevant, and other pertinent information which will adequately allow an assessment of the potential environmental impact by commenting agencies and the public.
DOC 335.08(3)(a)2.
2. An analysis of the probable impact of the proposed action on the environment of human beings, to include identification of positive as well as negative effects of the proposed action and, wherever possible, indirect as well as direct consequences for the environment.
DOC 335.08(3)(a)3.
3. Alternatives to the proposed action, including a rigorous exploration and objective evaluation of the environmental impacts of all reasonable alternatives, particularly those that might avoid all or some of the adverse environmental effects of the proposed action. If the department has a preferred alternative to the proposed action, that should be identified.
DOC 335.08(3)(a)4.
4. A discussion of probable adverse environmental effects which cannot be avoided should the proposal be implemented. Protective and mitigative measures to be taken as part of the proposed action shall be identified.
DOC 335.08(3)(a)5.
5. A discussion of the relationship between short-term use of the environment and the maintenance and enhancement of long-term productivity.
DOC 335.08(3)(a)6.
6. Identification of significant irreversible and irretrievable commitments of resources that would be involved in the proposed action, if implemented, with a statement identifying the extent to which the proposed action irreversibly curtails the range of potential uses of the environment.
DOC 335.08(3)(a)7.
7. Details of the beneficial aspects of the proposed action, and of the economic advantages and disadvantages of the proposed action.
DOC 335.08(3)(a)8.
8. A summary of the scoping process used and of the major issues identified through it for detailed analysis in the EIS.
DOC 335.08(3)(b)
(b) The EIS shall be an analytical document that enables environmental factors to be considered in the development of a proposed action. It shall be considered by the department in the decision-making process.
DOC 335.08(3)(c)
(c) An EIS is not a document of justification. On the other hand, disclosure of adverse environmental effects does not necessarily mean that a proposed action should be abandoned.
DOC 335.08(3)(d)
(d) Where proposed actions are likely to be repeated on a recurring basis or where they have relevant similarities such as common timing, impacts, alternatives, methods of implementation, or subject matter, a generic EIS may be prepared. The department shall, when addressing a single action already covered by a generic EIS, examine the relevance of the generic EIS to the specific action.
DOC 335.08 History
History: Cr.
Register, March, 1992, No. 435, eff. 4-1-92.
DOC 335.09(1)
(1)
Specified distribution. Copies of the DEIS shall be distributed to:
DOC 335.09(1)(b)
(b) The department of natural resources and other state, federal, and local government agencies having special expertise, interest or jurisdiction.
DOC 335.09(1)(c)
(c) Regional and county planning agencies located within the proposed project or action area.
DOC 335.09(1)(e)1.
1. For proposed actions affecting a local area, the nearest public library.
DOC 335.09(1)(e)2.
2. For projects of regional importance, public libraries with a geographic distribution which permits public access without undue travel.
DOC 335.09(1)(e)3.
3. For projects having statewide significance, public libraries providing reasonable access for individuals who could be affected by the proposed action.
DOC 335.09(1)(f)
(f) The county clerk, city clerk or town clerk for proposed actions affecting a local area.
DOC 335.09(1)(g)
(g) Any individual or group requesting a copy. Requests should be sent to the Division of Management Services, Department of Corrections, P.O. Box 7925, Madison, WI 53707-7925.